Project Scope:

  • Block 8 (Rooms 9 & 10)

o Remove x2 sets of exterior windows to each classroom.

o Install 3 door stackers.

o Remedial work to include existing wall linings and wall trims.

o Replace existing wall linings with new acoustic wall linings in both classrooms.

o In Room 10, replace existing ceiling baffles with new direct fixed acoustic

ceiling tiles.

  • Block 10 (Rooms 11 & 12)

o Replace existing carpet in both classrooms.

o Replace existing wall linings in corridor and install new acoustic wall linings to

display student artwork to modernise area.

o Paint interior.

o Fill in area of removed skylights and paint.

  • Block 10 (Boys & Girls Toilets)

o Remove and replace existing vinyl, WC pans, basin, toilet partitions.

o Supply and install new vinyl, WC pans, basins, taps, wall linings, toilet

partitions and hot water cylinder.

  • Block 11 (Rooms 14 & 15)

o Replace existing carpet in both classrooms.

o Replace existing wall linings in corridor and install new acoustic wall linings to

display student artwork to modernise area.

o Paint interior.

o Fill in area of removed skylights and paint.